ANKARA, Jan 27 (A.A) - Turkish companies won another auction abroad.
Turkish Barmek Holding's Barmek construction company undertook construction of 500-kilovolt (kv) Rewat transformer center within scope of the Pakistani Energy Ministry's Ghaziii-Baratha Hydroelectric Power Plant rehabilitation project to which also giant European energy companies like Alstom, Simens, ABB and Vatech submitted bids.
The sides are expected to sign a 8.5 million U.S. dollars of contract next week for rehabilitation of 500 kv Rewat transformer center in Islamabad, Pakistan.
Works on rehabilitation of the transformer center will be finalized in nearly 18 months and financed by the Islamic Development Bank loan.